Tongariro Chateau Car Park
Car Park Background
This car park was put in 8 years ago using geocell mats and gives a good example of the potential and durability of JakMat Geocell for this application.
Construction Steps
Jakaar has commissioned a registered engineer to give his recommendation of construction for a car park application using JakMat Geocell (see below).
Summary
Load bearing tests have also been performed on the JakMat which show high weight bearing strength (see below).
Test: JakMat packed with GAP 7 aggregate and compacted by hand. A 200mm x 9mm carbons steel plate disc was loaded as follows:
- Loaded to3500kg/34.4KN – No Visual Change Observed.
- Loaded to12910kg/126.6KN – 1.55mm deflection Observed
Contact us to discuss how JakMat can work for you.